Re: Costing Variant

$
0
0

Hi..

Rajneesh is right.

Instead to create costing variant, You can input bom usage directly when
you c
alculate standard cost using ck11 as below picture.

bs1.png

You can define bom usage for material’s costing in configuration of product cost controlling, under Base Settings for Material Costing->Material Cost Estimate with Quantity
Structure->Settings for Quantity Structure->BOM Selection->Check Alternative Selection for Multiple BOM.

BS2.png