we are creating manually the weekly schedule in the scheduling board - (APO DS).
It's quite a work and the constraints to create the sequence are not fully available.
We created a constraint XL sheet where to create the sequence (order list is imported from DS manual sequencing) - put them in the right sequence one by one, searching by order number and placing in the right position in the gant view
It's quite a work already with 20 orders per week - we have production lines with nearby 50 orders per week.
Once we have a defined sequence/schedule in XL should be possible to import it in DS - how does it work or is there any other way-of-work to have this task simplified-faster?
many thanks
Stefano