Hi Satyajit,
Thank you for your suggestion. Actually, the system calculates the planning periods based on planning parameters and created date of resources in SAP liveCache, so I re-transferred the work centre from R/3 to APO to update its saved date in liveCache. As a result, the planning period of resource is accordingly updated.
Cheers,
Danny