Possible scenario for issues components

 

1. Yes you can issue more components if your planned component is more than planned quantity with two different issue number.

 

Example 1:

 

Below screen planned quantitt 0.17 and issued quantity is 0.17. In this system won't allow you for another issue

 

 

12.JPG

 

 

 

 

Example 2:

 

If planned quantity is more than planned quantity (from BOM), then you can issue more components.

 

 

13.JPG

 

2. Possible to receive more than planned quantity of FG item. In normal case planned quantity of FG equal to receiving of FG item.

 

 

14.JPG

 

 

3. In short,

 

----> If your issued components are doubled, it Is not necessary  FG item also doubled

 

------> You can issue more components ( sufficient inventory) and you receive more FG part regardless of components

.

Thanks & Regards,